DEPARTMENT OF TRANSPORT —
METRIX CONSULTING RESEARCH
1318. Hon PETER COLLIER to the minister representing the
Minister for Transport:
I refer to the tender issued by the
Department of Transport titled ''Transport Infrastructure Creative
Services''.
(1) Who conducted the stage 1
research and what was the total cost?
(2) Who conducted the stage 2
research and what was the total cost?
(3) Will the minister table the
reports prepared from the stages 1 and 2 research; and, if not, why not?
(4) What was the cost of the Metrix
Consulting research?
(5) Will the minister table the
Metrix research; and, if not, why not?
Hon
STEPHEN DAWSON replied:
I thank the Leader of the Opposition
for some notice of the question.
(1)–(5) Metrix
completed stages 1 and 2 of the research, with stage 3 yet to be completed. The
total cost of the contract is $152 935.10. The research undertaken as part of
the contract is not yet complete.