BYFORD SOUTH EAST PRIMARY
SCHOOL
192. Hon DONNA FARAGHER to the Minister for Education and
Training:
I refer to Byford South East
Primary School.
(1) When is
construction of the new primary school expected to be completed?
(2) What is the
expected total project cost of the school building program at full stage
completion?
(3) What are the
most recent student enrolment projections for the new school at —
(a) the time of opening; and
(b) for the next five years after the
opening date?
Hon SUE
ELLERY replied:
I thank the honourable member for
some notice of the question.
(1) Construction
of the school is anticipated to be complete in December 2019, ready for opening
for the start of the 2020 school year.
(2) It is $18.9
million.
(3) Enrolment projections are based on 2018 student
enrolment data of the existing West Byford Primary School and Woodland
Grove Primary School, and planned residential development in the Byford area.
These projection estimates are highly
indicative, as parents' choice of moving their child from the existing
primary schools to the new local primary school will affect the future
student enrolments of the new school.
(a) It is 140
students.
(b) It is 200
students in 2021; 260 students in 2022; 400 students in 2023; 565 students in
2024; and 720 students in 2025.