Question Without Notice No. 619 asked in the Legislative Council on 21 August 2018 by Hon Peter Collier

Parliament: 40 Session: 1

OPTUS STADIUM — MATAGARUP BRIDGE

619. Hon PETER COLLIER to the minister representing the Minister for Transport:

I refer to the supply agreement between York Rizzani and the Bianco Engineering Services–Toyota Tsusho joint venture to manufacture the bridge decking and design features of the pedestrian footbridge to Optus Stadium.

(1) Which company was contracted to undertake the land-based formwork and construction for the bridge?

(2) At the time of the termination of the supply agreement, how much of the land-based formwork and construction had been completed?

Hon STEPHEN DAWSON replied:

I thank the honourable Leader of the Opposition for some notice of the question. Although it is unclear what the member is referring to by the term ''land-based formwork'', and given Main Roads' interpretation of the question, the answer is as follows.

(1) The concrete piers that form the substructure of the bridge and support the arches were completed by the York Rizzani joint venture.

(2) At the time of termination, these piers were complete.