Question Without Notice No. 654 asked in the Legislative Council on 16 August 2022 by Hon Dr Steve Thomas

Parliament: 41 Session: 1

LAPORTE JETTY — AUSTRALIND

654. Hon Dr STEVE THOMAS to the minister representing the Minister for Water:

I refer to Minister Kelly's media release of 15 August 2022 detailing the awarding of the refurbishment contract of Laporte jetty in Australind to Ventia.

(1) How many potential contractors submitted tenders for the Laporte–Australind jetty refurbishment?

(2) How many tenders were compliant and how many were noncompliant?

(3) When is on-the-ground refurbishment work scheduled to commence on the jetty and what is the allocated time frame for completion?

(4) Is the government of Western Australia, its departments or agencies responsible for future costs, upgrades and maintenance of the Laporte jetty post-refurbishment?

(5) If no to (4), who is responsible?

Hon ALANNAH MacTIERNAN replied:

I thank the member for the question. The following information has been provided to me by the Minister for Water.

(1) Nil. The refurbishment works are being undertaken through the Department of Transport's asset management and maintenance agreement with Ventia.

(2) Not applicable.

(3) In October 2022, subject to the completion of addressing environmental and Aboriginal heritage requirements. It is anticipated that refurbishment works will be completed in 2023.

(4) Yes.

(5) Not applicable.