Parliamentary Questions


Question Without Notice No. 677 asked in the Legislative Council on 17 August 2022 by Hon Dr Steve Thomas

Parliament: 41 Session: 1

SYNERGY — GENERATION OUTPUT

677. Hon Dr STEVE THOMAS to the parliamentary secretary representing the Minister for Energy:

I refer to question on notice 203 asked on 19 August 2021.

What was the total megawatt hour output of each Synergy generation plant, including coal, gas and renewable generation, in the 2021–22 financial year?

Hon MATTHEW SWINBOURN replied:

I thank the member for some notice of the question. The following information has been provided to me by the Minister for Energy. It is in tabular form so I seek leave to have the response incorporated into Hansard.

[Leave granted for the following material to be incorporated.]

Synergy Generation Plant

Plant Type

2021–22(GWh)

BREMER_BAY_WF1

Renewable

2

COCKBURN_CCG1

Gas

479

COLLIE_G1

Coal

1,136

KALBARRI_WF1

Renewable

1

KWINANA_GT2

Gas

381

KWINANA_GT3

Gas

391

MUJA_G5

Coal

743

MUJA_G6

Coal

731

MUJA_G7

Coal

1,143

MUJA_G8

Coal

1,232

MUNGARRA_GT1

Gas

2

MUNGARRA_GT3

Gas

2

PINJAR_GT1

Gas

11

PINJAR_GT10

Gas

52

PINJAR_GT11

Gas

178

PINJAR_GT2

Gas

6

PINJAR_GT3

Gas

8

PINJAR_GT4

Gas

7

PINJAR_GT5

Gas

9

PINJAR_GT7

Gas

10

PINJAR_GT9

Gas

170

WEST_KALGOORLIE_GT2

Distillate

3

WEST_KALGOORLIE_GT3

Distillate

2

Coral Bay

Renewable

2

Hopetoun

Renewable

2