Question Without Notice No. 813 asked in the Legislative Council on 14 October 2021 by Hon Dr Brad Pettitt

Parliament: 41 Session: 1

WATER — SOUTHERN SEAWATER DESALINATION PLANT

813. Hon Dr BRAD PETTITT to the minister representing the Minister for Water:

I refer to recent reports that the Water Corporation has failed to meet requirements of ministerial statement 792 to purchase renewable energy and offset the greenhouse gas emissions from the Southern Seawater Desalination Plant.

(1) When did the Water Corporation become aware of this noncompliance?

(2) How long has the ''process for returning SSDP to compliance � been protracted''?

(3) Has the Water Corporation achieved full compliance with requirements 792:M11–1 and 792:M12–l in any reporting years since production began in 2011?

(4) Has the Water Corporation surrendered any or all of the renewable energy certificates from purchasing renewable electricity as required?

Hon ALANNAH MacTIERNAN replied:

I thank the member for some notice of the question. The Minister for Water provides the following information.

(1) Water Corporation has been reporting publicly in the compliance assessment reports required by ministerial statement 792 that it has been noncompliant with condition 11-1 of ministerial statement 792 since 2015.

(2) Water Corporation has submitted a greenhouse gas management plan for the southern seawater desalination plant to the Department of Water and Environmental Regulation and is continuing discussions with that department as to its implementation.

(3)–(4) Yes.