Question Without Notice No. 410 asked in the Legislative Council on 7 May 2019 by Hon Colin Holt

Parliament: 40 Session: 1

PINJARRA PACEWAY — STALLS

410. Hon COLIN HOLT to the minister representing the Minister for Racing and Gaming:

I refer to the new stalls completed at Pinjarra paceway in December 2018.

(1) Why is there a delay in opening the new stalls?

(2) How much was spent on the new stalls and how much of the budget remains?

(3) If funds remain, what is the intention of Racing and Wagering Western Australia for the leftover funds?

(4) If further works are required, when can the Pinjarra Harness Racing Club expect these to be completed?

Hon ALANNAH MacTIERNAN replied:

I thank the member for the question. The following information has been provided by the Minister for Racing and Gaming.

(1) The delay in opening of stalls is due to a delay in the completion of the car park. The requirement to redesign the stormwater treatment from the car park has caused a delay in construction.

(2) The total project cost $3 110 744 and no moneys will be remaining once the car park is completed.

(3) Not applicable.

(4) The works will be completed by the end of May 2019.