Question Without Notice No. 123 asked in the Legislative Council on 20 February 2020 by Hon Martin Aldridge

Parliament: 40 Session: 1

GERALDTON HEALTH CAMPUS — REDEVELOPMENT

123. Hon MARTIN ALDRIDGE to the parliamentary secretary representing the Minister for Health:

I refer to the minister's media statement, ''Geraldton Health Campus redevelopment underway'', from 9 January 2020.

(1) How much funding has been expended to date on the Geraldton Health Campus redevelopment?

(2) What is the current expected date for construction to commence and for project completion?

(3) What is the projected total cost of the development?

(4) How many local contractors or service providers have been engaged to date on the project?

Hon ALANNA CLOHESY replied:

I thank the honourable member for some notice of the question.

(1) As at 31 January 2020, expenditure was $1 892 243.

(2) Construction is to commence in mid-2020 and practical completion is expected by late 2023.

(3) The projected total cost is $73.3 million.

(4) Two local contractors have been engaged to date.