Question Without Notice No. 686 asked in the Legislative Council on 28 August 2018 by Hon Peter Collier

Parliament: 40 Session: 1

OPTUS STADIUM — MATAGARUP BRIDGE

686. Hon PETER COLLIER to the minister representing the Minister for Transport:

I refer to the Matagarup Bridge.

(1) Has practical completion on the bridge been achieved?

(2) If no to (1), when is practical completion expected?

(3) If no to (1), who is now responsible for ongoing works to complete practical completion?

(4) If no to (1), who is liable for any accidents to the general public while using the bridge before practical completion?

(5) Did the York Rizzani joint venture seek, or were they provided by the government, any indemnities, guarantees or undertakings in relation to any injuries arising from the public accessing the bridge and surrounding works before practical completion?

(6) If yes to (5), what undertakings, indemnities or guarantees were provided?

Hon STEPHEN DAWSON replied:

I thank the honourable Leader of the Opposition for some notice of the question.

(1) No.

(2) Practical completion will be granted by Main Roads Western Australia when it is satisfied that the alliance has completed all the project works in accordance with the alliance agreement. It is anticipated that this will occur later this year.

(3) The alliance continues to be responsible for ongoing works to achieve practical completion.

(4) As the bridge is yet to reach practical completion, liability cover remains with the alliance in accordance with the terms set out in the alliance agreement.

(5) No.

(6) Not applicable.