Question Without Notice No. 193 asked in the Legislative Council on 12 March 2020 by Hon Tjorn Sibma

Parliament: 40 Session: 1

RAILCARS — MAINTENANCE CONTRACT

193. Hon TJORN SIBMA to the minister representing the Minister for Transport:

I refer to the contract signed with Alstom for the assembly and maintenance of trains.

(1) What is the value of the maintenance component in the contract with Alstom?

(2) What is the length of the maintenance contract with Alstom?

(3) What is the total number of jobs that will be created, broken down by maintenance, assembly and construction of the assembly facility?

Hon STEPHEN DAWSON replied:

I thank the honourable member for some notice of the question. The following answer has been provided by the Minister for Transport.

(1) The cost of the railcar contract is $1.25 billion, which is $347 million under the original budget.

(2) The initial term of the maintenance contract is 20 years, with two extension options of five years.

(3) Around 100 jobs are expected to be created during construction and more upon commissioning.