Secondary School Name | Estimated Cost ($) million | Status | Estimated Completion Date |
Butler North Senior High School * | 52.4 | Planning | December 2019 |
Byford Secondary College Stage 3 | 15.9 | Construction | October 2017 |
Cape Naturaliste College | 32.1 | In documentation | December 2019 |
Carine Senior High School | 18.8 | In documentation | September 2019 |
Carnarvon Community College Stage 2 | 17.6 | Construction | December 2017 |
Carnarvon Community College Stage 3 | 38.5 | In documentation | July 2019 |
Churchlands Senior High School | 34.6 | Construction | April 2018 |
Fremantle College | 30.0 | Construction | October 2017 |
Geraldton Senior College | 5.0 | Construction | January 2018 |
Inner City College * | 67.8 | Planning | January 2020 |
John Willcock College | 20.0 | At tender | January 2019 |
Joseph Banks Secondary College | 21.1 | Construction | August 2017 |
Margaret River Senior High School | 30.0 | Design and Development | December 2019 |
Shenton College Stage 2 | 49.5 | Construction | December 2018 |
South Baldivis Senior High School * | 47.9 | Construction | January 2019 |
Swan View Senior High School | 1.0 | Tender | December 2017 |
Yanchep Senior High School * | 50.4 | Construction | January 2018 |
Kalgoorlie-Boulder Community High School | 45.0 | Construction | December 2017 |
Warwick Senior High School | 5.0 | Tender | March 2018 |
Public Private Partnership Schools | | | |
Harrisdale Senior High School Stage 2 | | Planning | December 2019 |
North Ellenbrook Senior High School * | | Construction | December 2017 |
Lakelands Senior High School * | | Construction | December 2018 |
Hammond Park Senior High School * | | In documentation | December 2019 |