Question On Notice No. 2226 asked in the Legislative Council on 25 June 2019 by Hon Donna Faragher

Question Directed to the: Minister for Education and Training
Parliament: 40 Session: 1


Question

(1) I refer to Building Condition Assessment reports undertaken by the Department of Education for Western Australian public schools, and I ask for the financial years 2015-16, 2016-17, 2017-18 and 2018-19, what was the total amount of funding made available for maintenance at each of the following schools:
(a) Bungaree Primary School;
(b) Charthouse Primary School;
(c) Cooloongup Primary School;
(d) East Waikiki Primary School;
(e) Hillman Primary School;
(f) Malibu School;
(g) Rockingham Beach Education Support Centre;
(h) Rockingham Beach Primary School;
(i) Rockingham Senior High School;
(j) Rockingham Senior High School Education Support Centre;
(k) Safety Bay Primary School; and
(l) Safety Bay Senior High School?
(2) For all schools referred to in (1), what is the amount to be made available for maintenance in 2019-20?

Answered on 20 August 2019

1)

SCHOOL

2015-16

($)

2016-17

($)

2017-18

($)

2018-19

($)

TOTAL

($)

a)         Bungaree Primary School

435 976

128 572

241 264

220 306

1 026 118

b)         Charthouse Primary School

124 036

187 607

205 746

178 145

695 534

c)         Cooloongup Primary School

563 552

133 014

38 195

565 090

1 299 851

d)         East Waikiki Primary School

90 180

108 391

219 609

1 091 680

1 509 860

e)         Hillman Primary School

144 691

125 796

79 356

87 712

437 555

f)          Malibu School

656 931

197 388

436 128

127 708

1 418 155

g)         Rockingham Beach

Education Support Centre*

-

-

-

-

-

h)         Rockingham Beach Primary School

360 443

194 127

194 042

687 485

1 436 097

i)          Rockingham Senior High School

805 469

536 170

756 068

475 983

2 573 690

j)          Rockingham Senior High School

Education Support Centre*

-

-

-

-

-

k)         Safety Bay Primary School

117 416

144 806

107 227

138 867

508 316

l)          Safety Bay Senior High School

721 539

718 494

530 700

688 229

2 658 962

Data Source:        

Department of Finance Building Management and Works (BMW) Data Warehouse 2018-19 data as at 24 June 2019. Includes expenditures funded by schools where works were arranged by BMW 

*          Rockingham Beach Education Support Centre is included with Rockingham Beach Primary School. Rockingham Senior High School Education Support Centre is included with Rockingham Senior High School. 

2)         Funding is managed centrally and is allocated to address needs in schools as they arise.  Schools may elect to manage their own faults and breakdowns up to a maximum of $5000 per event and receive an allocation from the central maintenance account. Schools may also use part of their one-line budget to undertake maintenance and minor works projects.