Question On Notice No. 644 asked in the Legislative Assembly on 1 December 2022 by Mr R.S. Love
Question Directed to the: Minister for Transport
Parliament: 41 Session: 1
Question
Regarding the Bayswater Station
:
(a) Please detail the updated construction timeline;
(b) Please detail the updated cost of the project;
(c) How will the collapse of Firm Construction impact:
(i) The delivery of the project; and
(ii) Payments to subcontractors; and
(d) With respect to compensation for businesses and residents, how many cases remain outstanding?
Answered on 14 February 2023
- The New Bayswater Station Project will be completed in line with the Morley-Ellenbrook Line opening.
- The budget is unchanged.
- The main contractor, Evolve Bayswater, is taking responsibility of all sub-contracts previously managed by FIRM Construction. There is currently no impact to the existing timeframes or payments to subcontractors.
- Residential compensation claims are assessed at project completion. The project is currently working through one business compensation claim.