Question

I refer to the ongoing escalator issues on the Joondalup line, and I ask:
(a) When are maintenance works expected to begin at the Whitfords and Warwick train stations;
(b) What is the anticipated timeframe to complete the works at both train stations;
(c) With reference to the Joondalup Times article of 18 June 2020, will costs for these works be met by the contractor;
(d) If no to (c), what is the anticipated cost to the taxpayer to compete the works on the Joondalup line; and
(e) Will there be appropriate signage at each train station notifying patrons of the planned works?

Answered on 18 August 2020

(a)-(b) One escalator at each station were repaired in April 2020. Repairs on the remaining machines at Whitfords and Warwick will commence in the coming months.

(c) A Deed of Settlement agreement has been implemented and the issues will be rectified at the cost of the supplier.

(d) Not applicable

(e) Yes