Question On Notice No. 1176 asked in the Legislative Council on 1 December 2022 by Hon Dr Brad Pettitt
Question Directed to the: Leader of the House representing the Minister for Transport
Parliament: 41 Session: 1
Question
I refer to the completed High Street upgrade from Stirling Highway to
Carrington Street, noting the response to question on notice 263, and I ask
for the Minister to provide:
(a) the
total number of large trees retained in the project area;
(b) the
total number of established tuart trees retained in the project area;
(c) the
total number of new trees planted in the project area;
(d) the
total number of new large trees planted in the project area; and
(e) and
any plans to plant additional trees in the project area, and a timeline for
completion of these plans?
Answered on 14 February 2023
- 153.
- 12.
- 1,709.
- 117.
- Remaining revegetation activity will take place over the next two winters to give the new trees the optimum chance of success.