Question Without Notice No. 702 asked in the Legislative Council on 14 September 2021 by Hon Dr Brian Walker

Parliament: 41 Session: 1

MANDURAH RAIL LINE — CLOSURE

702. Hon Dr BRIAN WALKER to the Leader of the House representing the Minister for Transport:

I refer the minister to the Treasurer's budget announcement last week in which he indicated that there would be a 12-month delay in the delivery of various Metronet promises, including the activation of the Thornlie–Cockburn Link. Can the minister please confirm whether this means that the proposed month-long closure of the Mandurah line will be rescheduled or will it go ahead as planned, with commuters being asked to bear the pain without any immediate gain?

Hon SUE ELLERY replied:

I thank the honourable member for some notice of the question.

The Mandurah line shutdown will commence on 26 December 2021 and will deliver critical enabling works on the Metronet Thornlie–Cockburn Link. We will continue to engage with the local community on minimising impacts on travel over this period.