Question Without Notice No. 382 asked in the Legislative Council on 11 May 2022 by Hon Dr Brian Walker

Parliament: 41 Session: 1

METRONET — BAYSWATER STATION CONTRACTOR

382. Hon Dr BRIAN WALKER to the Leader of the House representing the Minister for Transport:

I refer the minister to a report published in The Perth Voice of 28 April 2022 suggesting that the government has listened to local concerns in Bayswater, agreeing to relocate the construction headquarters for the Bayswater station contractor somewhere other than Mills Avenue Park. I commend the minister for his flexible approach and ask —

(1) What consultations are underway at present to identify an alternate location and with whom has the Metronet team or the department as a whole liaised to date?

(2) What time constraints exist when it comes to identifying an alternative site to allow the work to proceed on schedule?

(3) Have any potential sites been identified thus far; and, if so, where?

Hon SUE ELLERY replied:

I thank the honourable member for some notice of the question.

(1) The project team is working closely with the City of Bayswater to find a suitable location and will liaise with residents neighbouring the proposed sites.

(2) The site facilities must be relocated before July 2022.

(3) The project team has worked with City of Bayswater staff to identify three sites that could all be utilised for separate purposes at an unused car park at Frank Drago Reserve; a vacant block on Railway Parade; and along Whatley Crescent.